Vistry’s night-time working is booked for site investigation works from 16th Sept to 5th October (8:00PM to 06:00AM) for the A1 slip roads off the A52 Barrowby Road.
Coun Richard Davies says: “We have requested that the start time be amended to working between 9:30PM and 05:30AM and we’re awaiting a response.
“Only a tiny element of this is on the LCC network; the bulk of the work is on National Highways slip roads, which they approved”.”
The investigation works include:-
• Vegetation clearance
• CCTV surveys of drainage
• CBR testing
• Borehole investigations
• Coring
To enable Vistry to undertake these works, temporary lane closures with traffic signals and full slip lane closures will be in place during night-time working.
All roads and slip roads will be fully open between 6 a.m. and 8 p.m., and access will be maintained to all properties and businesses at all times.
Diversionary routes from the A1 will also be signposted during slip road closures.
Leave a Reply
You must be logged in to post a comment.