The bridge launch on the Grantham Southern Relief Road has been completed, according to Lincolnshire County Council’s latest monthly update.
On the west side of the site, launch equipment was being removed during October and work continued on assembling an access gantry. On the east side, temporary works were installed at Pier 5 and sections of the bridge’s temporary launch nose were removed.
In November, the access gantry is due to be finished and more launch equipment removed. Work will also start on filling the western embankment, which will use more than 100,000 tonnes of material.
On the east side, the temporary works at Pier 5 will start to be removed, along with more of the temporary strengthening plates on Span 5. Fill material will also be moved from the allotment area to the west embankment.
Lane restrictions are still in place around the B1174 roundabout while the haul route and site access are built. No further restrictions or closures have been announced.
The latest project and traffic updates are on the council’s website.