This month topsoiling will be completed on the west side of the side, whilst excavations begin on the east side.
What we achieved in May
Phase Two
- Installation of signage under night-time southbound A1 lane closure
Phase Three
- West side of site – continue out topsoiling and finishing works near Pond B
- East side of site – complete Pier 5 piling platform / continue piling to the east abutment and started Pier 5 piling / opened Whalebone Lane to traffic on 5th May
What’s happening in June
Phase Three
- West side of site – complete topsoiling and finishing works near Pond B
- East side of site – complete Pier 5 piling / begin excavation and pile cropping to Pier 5 / continue piling to the east abutment / complete white lining / open Whalebone Lane to traffic
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- Temporary traffic signals as required for white lining of Whalebone Lane
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.