Phase two and three work continues.
What was achieved in December
Phase Two
- Opened Phase Two of Grantham Southern Relief Road, which connects the A1 and B1174
- Laid lining and high friction surfacing on new section of A1
- Installed signage for the new A1 junction with the relief road
Phase Three
- West side of site – carry out works to concrete infills at Pier 3 / install drainage and continue finishing works to Pond B / install filter drains near the west embankment
- East side of side – complete verge finishings at Whalebone Lane / continue Pier 4 concreting works / sub-base trim at development roundabout / excavate and remove east embankment back to the location of the new east abutment
What’s happening in January
Phase Three
- West side of site – continue concrete infills at Piers 1 and 2 / complete drainage to Pond B / continue drainage works near the west embankment
- East side of side – continue Pier 4 concreting works / complete excavation of east embankment back to the location of the new east abutment / carry out kerbing installation and surfacing at development roundabout / complete surfacing between Whalebone Lane and development roundabout
Current/ongoing traffic restrictions and closures
- Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
- Whalebone Lane closed
- Lane restrictions around Somerby Hill Roundabout
Upcoming traffic restrictions and closures
- N/A
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.