A series of A1 closures will be in place in April and May.
Below is a list of upcoming closures on the A1 near Grantham (subject to weather):
Night-time northbound A1 closure / Tuesday 19 April for up to four evenings, 8pm to 6am
Diversion route via the B1174 / A52 / A607 / B1174, and vice versa
Night-time southbound A1 closure / Tuesday 3 May for up to four evenings, 8pm to 6am
Diversion route via the B1174 / A52 / A607 / B1174, and vice versa
Weekend northbound A1 closure / 8pm on Friday 20 May to 6am on Monday 23 May
Diversion route via A606 at Stamford through Melton Mowbray to re-join A1 via A607 at Harlaxton
Cllr Richard Davies, executive member for highways, said: “These upcoming A1 closures will allow Galliford Try a safe timeframe to carry out additional drainage, street-lighting, verge and final bridge joint works on the A1 near Grantham as part of our ongoing relief road project.
“Each of these will no doubt cause some disruption, particularly the weekend closure starting Friday 20 May, so we encourage people to plan accordingly and leave extra time for their journeys.
“Despite the second phase of the relief road project being all but complete, we won’t be opening the A1 new connection until a bit further down the line.
“This will not only ensure the safety of those working at the Tollemache Road site compound, but will also allow National Highways time to complete all their checks and for the site team to complete any required final works.
“In the meantime, phase three is progressing ahead really well, and we’re still on track for having the entire relief road opened in 2023.”
The Grantham Southern Relief Road project is being led by Lincolnshire County Council and supported by South Kesteven District Council, Greater Lincolnshire LEP, Highways England, Department for Transport, Network Rail, Homes England and local businesses.
For the latest news on the Grantham Southern Relief Road, visit www.lincolnshire.gov.uk/majorprojects.