The latest update on the Grantham Southern Relief Road.
What we achieved in October
Phase Three
- East side of site – completed sub-base to eastern embankment / concreting to in line wingwalls / fixed reinforcement, concrete and shuttering to ballast wall
What’s happening in November
Phase Three
- East side of site – strip ballast wall shutters / delivery of Span 7 bridge beams / slice beams together / install temporary works to eastern abutment and Pier 6 for beam lift
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A