What we achieved in October and what we have planned for November.
What we achieved in October
Phase Three
- West side of site – backfilled Pier 3 excavations / installed Pier 1 / began surcharge works to the west embankment
- East side of site – continued Whalebone Lane surfacing / installed narrow filter drain and started construction of grass channel near Whalebone Lane / excavated crop piles / began concreting works to Pier 4 / install liner to Pond A / began planting works at Somerby Hill Roundabout
What’s happening in November
Phase Two
- Carry out final street light earthing, testing and commissioning on the A1
Phase Three
- West side of site – install Pier 2 and Pier 3 / install liner to Pond B
- East side of side – continue construction of grass channel at Whalebone Lane / continue Pier 4 concreting works / begin laying sub-base and installing kerbing and gullies to development roundabout / divert quarry traffic from old Whalebone Lane to the new road / complete planting works at Somerby Hill Roundabout
Current/ongoing traffic restrictions and closures
- Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
- Whalebone Lane closed
- Lane restrictions around Somerby Hill Roundabout
Upcoming traffic restrictions and closures
- Overnight A1 northbound lane 1 closure; Tuesday 15 November for up to four evenings, 8pm to 6am
- Overnight A1 southbound lane 1 closure; Monday 21 November for up to five evenings, 8pm to 6am
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.