Phase three works continuing ahead.
What was achieved in September
Phase Three
- West side of site – pier 3 bases concreted / pier 2 upstands concreted / pier 3 upstands concreted
- East side of site – excavate plug of earth at Whalebone Lane / roadbox and surfacing between Whalebone and Development / complete Piling at Pier 4 / excavate cofferdam at Pier 4 / complete Infiltration Trenches between Whalebone and Development
What’s happening in October
Phase Three
- West side of site – Backfill Pier 3 excavations / Install Piers 1, 2 & 3 / Install Liner to Pond B
- East side of side – Surfacing from Whalebone Lane to Ch1400 / Installation of Narrow Filter Drain & Grass Channel Whalebone Lane to Ch1400 / Excavate and Crop Piles @ Pier 4 / Begin FRC Works to Pier 4 / Install Liner to Pond A
Current/ongoing traffic restrictions and closures
- Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the Haul Route and Access into site.
- Whalebone Lane Closed
- Lane Restrictions around Somerby Hill Roundabout.
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.
Published: 4th October 2022